*SCHEDULING: How to Complete the Work Activity
OVERVIEW:
Completing the activity in the Calendar has a direct effect on the invoicing so is VERY IMPORTANT not to miss this step.
We encourage your scheduler to do these actions/checks on a daily basis.
The right click is a handy tool for when completing activities on the Calendar.
1. Right click on the activity and set to DONE 100% when that pice of work is fully done.
2. Right click on the activity and click # DONE Partially and a box will appear for you to insert the % done (Do NOT choose ongoing done).

Examples of what your Calendar Activities will look like
0. No % Done - NOTE this now shows nothing
1. 100% Done
2. 45% Done
3. A tick indicates activity has been invoiced